Project Task Progress Update in Project Operations & Mark Task as Completed

Up until now, you had to do Time Entries to mark a Project Task as completed. But, this makes difficult to gauge the progress of the project in actuality as some tasks might need to be marked as completed without having to do remaining Time Entries on them.

Here’s when marking Project Task as Completed comes in handy.

Default Behavior for Project Tasks in Project Operations

By default, you won’t be able to edit the % of the task in the Project Task Grid –

  1. Till now, you are able to directly mark a Task as complete by using the below option –

  2. And it’ll mark the task as Completed to 100%. But, when hover over the % completed, it’ll say that it’s a read-only and can’t be edited to put your custom % in there.

  3. So, let’s see how this feature will let you edit the % complete to your desired number.

Enable marking Project Tasks as completed

In Project Parameters, you can find the Feature to mark Project Task as completed –

  1. Drop down on the Feature Control and you’ll see that Task C

Mark Project Tasks as completed

When you enable this, you’ll see the below on the Project –

  1. The Project form will have the field to allow Project Tasks to have custom progress % option.

  2. Once you do this, you’ll then be able to hover over the Project Task and enter the % you desire.

Hope this was useful!

Thank you!

Cost Plus Billing in Project Operations

Here’s how your Project Contract can be setup for Cost Plus Billing in Project Operations –

So how does Cost Plus Pricing work? Simple Answer – Specify a Markup for the Sales price in terms of % based on what the Cost Price is.

So, when you enter the Sales Prices without having Cost Plus Pricing Enabled, you’ll see that you simply can enter the Sales Price of the Resource as shown below

Now, let’s see how you specify the Cost Plus pricing in Sales Price Lists so that it is driven off of the Markup of the % of the Cost Price.

Enable Cost Plus Pricing from Project Parameters

First, you need to enable Cost Plus Pricing in your Project Operations environment –

  1. Given you have the correct access, navigate to Project Parameters settings in your environment and look for the Feature Control where it says that you can enable Cost Plus Pricing –

  2. It’ll give you a warning that once this is enabled, you cannot disable it for the organization –


  3. Now, when you try to add Role Prices in the Sales Price List, you can select this option –

  4. And enter the % of the Markup you want to setup for Cost Plus Pricing.

  5. In this case, my Markup is 25% of the Cost Price.

  6. Now, my Cost Price for the Marketing Manager Role is $200.

  7. Now, given that my Project Contract has Project Contract Line is this Role, the Amount will be determined based on this Markup. Here, I’ve quoted 100 hours for the Marketing Manager Role which makes the Cost Price as $20,000 and the Sale Price as $25,000.

  8. Now, when the Unbilled Actuals is created, it’ll consider the 25% Markup for the Marketing Manager role and calculate the Billing Amount i.e. $250 which is a Markup of 25% on top of $200.


Hope this was useful!

Thank you!

Multi-currency Cost Price List in Project Operations Lite

Here’s how you can have a Global Price List under an Org Unit without tying it to the currency of the base Org Unit which is the Default use case.

Currently, here’s how the default behavior is without having the multi-currency cost price list disabled –

Now, let’s see how this will change when we have the Multi-currency cost price list enabled for your environment.

Multi-currency Cost Price List

This can be enabled from Project Parameters. Here’s how you do this provided you have the correct access –

  1. Go to Project Parameter record in PO Lite, you’ll see this – which you can select Yes and save to enable it.



  2. When you enable, it’ll show this message before you confirm –
    You are changing the way a Cost Price List is selected by system. The setting you are choosing indicates that the system will no longer select a cost price by matching the currency of the price list with the currency of the contracting unit. Any cost price list irrespective of currency could be selected as long as it is applicable for the date. Please ensure that you understand the impact before making this change. Please note that this will impact cost price list defaulting for ongoing projects as well.


  3. Now, when you have the same enabled, you’ll be able to add a Cost Price list of different currency than that of the Organization Unit.


  4. If you see above, the different currencies can exist for the Organization which has a certain currency.

Behavior

Here’s a caveat when you select a multi-currency Cost Price List still

  1. You cannot have the Start and End Dates overlap each other even when you have different currencies. When you try to do this, it’ll give you the below error.

  2. When Time Entries are made, the Inter-Organizational Sales Actuals are also created based on the Cost Price from that Price List.





Being able to schedule for Resources across multiple geographies

Thank you!